Cinderpoint › Books › Data Center Buildout › Power Bills and the Grid
Chapter 4 of 26  ·  Data Center Buildout

Power Bills and the Grid

From Data Center Buildout: Money, Politics, Environment, & Energy Behind AI Growth  ·  Waydell D. Carvalho

Described in Data Center Buildout by Waydell D. Carvalho.

Definition
When a data center sits next to a power plant, who pays for the grid it still leans on? The chapter tests the cost-shift claim in the Amazon and Talen case at the Susquehanna nuclear plant.
What Each Side Claims
  • Talen: direct connection is fast and reliable
  • Utilities: Amazon would not pay for backup
  • Federal regulator: the template stands unless justified

What the record shows: The regulator ruled on the burden of proof. It did not find that a cost shift occurred.

On November 1, 2024, three federal energy commissioners voted on what looked like paperwork. The paper was an amended contract to connect a power plant to the grid. It covered Talen Energy's Susquehanna nuclear plant in Pennsylvania. The change would have raised the data center load next door from 300 to 480 megawatts. Reports say the load was an Amazon Web Services data center.

Most of its power would flow straight from the plant to the data center, behind the meter. But reactors shut down for maintenance and refueling. Exelon, AEP, and the grid's market monitor argued that the data center would then lean on the shared grid for backup. Susquehanna said its design would stop any grid draw.

The vote

The vote was 2 to 1. The majority held that the grid operator, PJM, had not justified leaving the standard agreement. The ruling was about proof. It did not find that other customers would pay more. Exelon and AEP put the shift at as much as $140 million a year. That was their own estimate, and Susquehanna said it was not accurate. The regulator did not adopt it.

Chairman Willie Phillips dissented. He called the ruling a step backward for reliability and national security. The majority replied that the dissent offered no details on how the order would hurt either one.

The industry mostly routed around the vote. Talen agreed in 2025 to move the Amazon load to the front of the meter. In June 2025, Talen and Amazon announced a larger supply deal of 1,920 megawatts running through 2042.

Bills and the wider grid

The grid's price pressure has more than one cause. PJM's July 2024 capacity auction cleared at $269.92 per megawatt-day, up from $28.92 a year earlier. A report for the D.C. consumer counsel names four drivers: retirements, demand growth, new accreditation rules, and slow interconnection queues. Data center load is a real driver, but not the only one.

In El Paso, a utility filed to build a 366-megawatt gas plant for a data center that the city identified as Meta's. The filing says the data center would pay the plant's capital costs for a bridge period of up to five years. The residential ratepayer is the one party the record never lets speak for itself. The filings behind this fight are laid out in Data Center Buildout.

This chapter is examined in full in Data Center Buildout: Money, Politics, Environment, & Energy Behind AI Growth by Waydell D. Carvalho. All 26 Chapters are developed and connected in the complete book.
Get the book ↗
Cite this concept
Carvalho, W. D. (2026). Power Bills and the Grid. Cinderpoint. https://cinderpoint.com/library/data-center-buildout/power-bills-and-the-grid/