Land Use
Described in Data Center Buildout by Waydell D. Carvalho.
- Developers: a hub that brings tax revenue
- Opponents: harm to the battlefield and neighbors
- Courts: the county missed its own notice rules
What the record shows: The rezoning fell on a notice statute, not on the battlefield or the tax numbers.
In mid-December 2023, the Prince William County Board of Supervisors approved what trade press called the world's largest data center hub. It allowed as many as 37 data centers next to Manassas National Battlefield Park, on roughly 1,760 to 1,790 acres. The vote was 4 to 3, with one abstention. The public hearing before it ran about 27 hours.
Two developers, QTS and Compass, had assembled land from landowners along Pageland Lane. The buildings would sit in the county's Rural Crescent and near the battlefield. A QTS statement after the vote said the project was projected to bring an estimated $500 million in annual tax revenue. It gave no projection to back that up, so the chapter treats the number as a developer claim.
The suit that won
On January 12, 2024, lawyer Chap Petersen announced a suit with nearby residents and the American Battlefield Trust. A separate suit came from the Oak Valley Homeowners Association. The case did not ask a court to weigh the battlefield against the buildings. It asked one narrow question. Had the county given the notice that state law and its own code required?
Judge Kimberly Irving said no. State law requires two notices a week apart, and the proposed text must be open to the public. The county's first scheduled ad never ran. The text was not available until December 7, five days before the hearing. She found that the county alone caused the defects.
The Virginia Court of Appeals affirmed in March 2026. Compass declined to appeal further. QTS appealed alone and then withdrew on July 2, 2026, giving no reasons beyond careful consideration. The Digital Gateway is dead.
The lesson of a dull rule
The chapter notes that the preservation frame drew the political energy and much of the news coverage. A ruling on the battlefield would have set a broader rule. A ruling on notice sets a narrow one, but it is a published appeals opinion with statewide effect.
For a resident, notice is a checkpoint that can be checked against the statute. Proving the defect still took depositions, records, and a five-day trial. The window to file a notice challenge closes 30 days after the vote. The rule that decided this case is the dullest one in the process. Data Center Buildout follows the notice record from the first ad to the withdrawal.