Federal Preemption
Described in Data Center Buildout by Waydell D. Carvalho.
- Industry: slow federal permits hurt the race with China
- Opponents: the order narrows review on a fast clock
- Washington: speed up permits and block state AI laws
What the record shows: The order has no preemption clause. It works by cutting federal review above state and county decisions.
On April 2, 2026, the federal permitting council announced a first. QTS Richmond Technology Park Data Center 5 became the first data center project in the country covered by FAST-41. That 2015 law sets a public timetable for federal permits. The council says it changes no environmental law. It holds agencies to a schedule.
The project followed an executive order signed July 23, 2025. The order has no clause that overrides state law. What it does is restructure the federal review that stands above state and county decisions. It covers projects that cost at least $500 million, add over 100 megawatts of load, or serve national security.
Five changes
The order did five things. It told agencies to write shortcuts around full review. It set a rule that federal help below 50 percent of costs does not count as federal control. That narrows when the main review law applies. It opened FAST-41 to data centers. It called for bundled wildlife and water permits. And it opened federal land. The Energy Department named four sites a day later. The Air Force offered 3,101 acres in October 2025.
The industry case fits in one line from the Data Center Coalition: speeding up permits is critical to keeping pace with demand. Part of that case is documented. Only 39 percent of federal impact statements finished within two years. The China comparison is harder to pin down.
The old emergency law
A 1935 law lets the Secretary of Energy order grid connections in an emergency. The department used it once in 2023, once in 2024, and 16 times in 2025. It issued 37 orders from January to July 2026. Eight let grid operators direct backup power at data centers and other large sites.
Congress was also asked to bar state AI laws. In July 2025 the Senate struck a 10-year moratorium by a vote of 99 to 1. In December 2025, an executive order revived the goal and created a Justice Department task force to challenge state AI laws. No court had ruled against the toolkit in the sources by summer 2026.
The pieces are not new, and each has defenders across the spectrum. The record carries opposition to bundling them into one fast package. Data Center Buildout covers the order, the emergency dispatches, and the court record.