Cinderpoint › Books › Data Center Buildout › Jurisdictional Bypass
Chapter 8 of 26  ·  Data Center Buildout

Jurisdictional Bypass

From Data Center Buildout: Money, Politics, Environment, & Energy Behind AI Growth  ·  Waydell D. Carvalho

Described in Data Center Buildout by Waydell D. Carvalho.

Definition
Can one project survive a no from one government if other governments hold other pieces of it? The chapter tests this with Project Blue, a data center plan near Tucson, Arizona.
What Each Side Claims
  • Developer: water positive, with a tax benefit
  • Residents: too much water and power for the region
  • Commission: it approves financial terms, not the project

What the record shows: Each body answered only its own narrow question, and the project went on in pieces.

On August 6, 2025, the Tucson City Council voted 7 to 0 to end talks with the developer of Project Blue and drop annexation. The developer wanted the land annexed to get city water. About 1,000 residents had packed a community meeting two nights before. Reports named Amazon Web Services as the tenant.

That was one of three answers. The project sat on a 290-acre parcel in unincorporated Pima County. The county board voted 3 to 2 on June 17 to approve the land sale. The Arizona Corporation Commission voted 4 to 1 on December 3 to approve a special power agreement. Two bodies said yes and one said no.

Three governments, three questions

Each government answered only the question it controlled. The county held the land sale. The city held annexation, and its water and zoning went with that choice. The commission held the power to approve the terms on which the utility served a customer. None of them decided whether to build the project.

Commissioner Lea Marquez Peterson said the commission was not approving or disapproving Project Blue. She said it was approving financial terms to protect ratepayers. The utility's commitment was about 286 megawatts by 2028. A county supervisor said the filing was designed to bypass the community's will. That is his characterization.

The tenant stayed unconfirmed. Press reports cite anonymous sources saying Amazon left on December 2, after the design moved toward air cooling. Neither company confirmed it. The reports say the city had refused the water the first cooling plans needed.

The residents' side

A coalition formed in weeks. It turned acre-feet and megawatts into golf courses and homes. It also named which vote residents still had a say in. Those two moves worked in the city chamber. The commission's docket favored parties who appeared at length.

Arizona's Attorney General Kris Mayes filed an appeal in February 2026. She argues the agreement lets the utility and the developer change rates between themselves, and that the commission cannot give that power away. The appeal was still pending in late September 2026. A project that can go forward in pieces does not have to win every vote. The three votes are traced step by step in Data Center Buildout.

This chapter is examined in full in Data Center Buildout: Money, Politics, Environment, & Energy Behind AI Growth by Waydell D. Carvalho. All 26 Chapters are developed and connected in the complete book.
Get the book ↗
Cite this concept
Carvalho, W. D. (2026). Jurisdictional Bypass. Cinderpoint. https://cinderpoint.com/library/data-center-buildout/jurisdictional-bypass/